Does the supply cable between the Siemens soft starter and the motor need shielding
Published:2023-02-06 16:12:46
For 3RW soft starters, it is sufficient to use an unshielded main loop cable between the motor and the 3RW soft starter.
The main reasons are as follows:
The frequency of the power supply on the motor terminal is steady at 50 or 60 Hz throughout the soft starter operation
After the soft start is complete, the main loop switches to the internal bypass contactor in parallel, and the current and voltage waveforms are perfect sine waves.
The soft starter is operated using phase Angle control during soft start and soft stop. Phase Angle control achieves the purpose of step-down starting by controlling the thyristor turn-on time. Only when the pulse triggers the thyristor turn-on, the harmonic wave will be generated, and the duration is very short. So it's negligible.
-
202212-30
What are the main items of Omron plc overhaul?
1. Check the power supply. Check whether the voltage change range at the power terminal is within the allowable ±10% range.2. Work environment. Focus on checking whether the temperature, humidity, vi···
-
202302-27
How does Delta inverter adjust the frequency?
Delta frequency converter, frequency adjustment is mainly operated in the control panel, process:1. Press the Menu button to enter the parameter programming menu.2, P0.01=1, input this parameter to co···
-
202302-02
Mitsubishi inverter overload fault judgment method
1. Check whether the three-phase power of the motor is balanced(1) If the three-phase voltage of the motor is not balanced, the three-phase voltage of the output end of the Mitsubishi inverter should ···
-
202302-10
How to choose Omron relay
1, select the rated working current of electromagnetic relay coil: DC electromagnetic relay driven by transistor or integrated circuit, the rated working current of the coil (generally 2 times of the ···
-
202301-12
Delta UPS uninterruptible power supply basic conditions
1. Visually inspect the UPS and battery (or other energy storage) equipment for obstructions and properly cool the surrounding area.2. Ensure that there is no abnormal operation or warning on the UPS ···