General steps for ABB robot installation and commissioning:
1. Lift the robot body and control cabinet into place
2. Cable connection between ABB robot body and control cabinet
3. ABB robot teaching device is connected with control cabinet
4. Connect to the main power supply
5, check the main power supply is normal, power on
6. Calibration operation of mechanical origin of six axes of the robot
7. Setting of 1/0 signal
8. Install tools and peripheral equipment
9. Programming and debugging
10. Put into automatic operation
Basic debugging methods/steps of abb robot accessories
1. System information Displays the relevant information of the controller and the operating system. You can view the version and option of RobotWare currently in use, the current key of the control and driver module, and the network connection.
2. The robot system needs to be restarted under the following circumstances:
1) New hardware has been installed.
2) The configuration parameters of the robot system are changed.
3) System failure (SYSFAIL)
4) The RAPID program has a program fault.
Matters needing attention
ABB robotic systems can be unmanned for long periods of time. There is no need to periodically restart a running system.
-
202302-13
Mitsubishi PLC source type and leakage type difference
Mitsubishi PLC split source type (PNP) or leak type (NPN), the following is their difference1: Leaky logic: When current flows out of the signal input terminal, the signal changes to ON, indicating le···
-
202303-03
How to set the English window of MCGS touch screen
Open the Kunlun touch screen programming software and select the Multi-Language Configuration icon from the Edit menuIn the Multilingual Configuration window that appears, select File and click Open.S···
-
202302-08
Schneider PLC control cabinet installation wiring method
(1) When placing signal cables with different properties into the same conduit, they must be isolated② Try to avoid multiple power lines contained in the same catheter. If necessary, a partition shal···
-
202212-29
This section describes how to set a gateway for Advantech switch eki-2528
step 1: Configure a VLAN. You are advised to allocate a dedicated VLAN, for example, VLAN 1000, for the management IP address of the switch on the network.Configuration command: vlan 1000step 2: Set a···
-
202302-13
Mitsubishi PLC communication detection steps
When you are ready to communicate through the AJ71QE71, perform the ping procedure in MS-DOS mode before starting the communication with Mitsubishi PLC's GPPW to see if the connection is correct. ···